FUTURE ENERGY INNOVATION & TRAINING HUB (FEITH)

ICON FEITH REVERSED

Overview

This state-of-the-art precinct is part of Stanwell’s overall approach to delivering clean energy and is located at the Stanwell Power Station in central Queensland. The Future Energy and Training Hub (FEITH) will provide a pilot and testing facility for new energy technologies as well as a renewable energies education and training facility. The project is also part of the transition of the Stanwell Power Station into a Clean Energy Hub by 2035.

Technical details

The project (the size of a shopping centre) will be built in four phases. When complete – the precinct will include:

  • A state-of-the-art workforce skills and technical training Academy.

  • An installation to demonstrate to the community a range of energy technologies and hydrogen applications.

  • A world-class commercial-scale research and testing precinct for medium to long-duration battery storage, transmission, and renewable energy integration technologies.

  • A servicing and maintenance workshop for clean energy.

Project timeline

This project has multiple components which are happening concurrently on site:

Overarching infrastructure, services and Hysata’s hydrogen test site

Dec 2024: Contractor appointed

Sep 2025: Civil works to commence - expected to take six to seven months

Mar 2026: Commissioning and testing of common infrastructure services and Hysata’s hydrogen electrolyser

Solar installation

Oct 2024: Contractor appointed

Mar 2025: Civil works to commence - expected to take six to seven months

Oct 2025: Commissioning

Iron Flow Battery (IFB) testing site

June 2024: Contractor appointed

Nov 2024: Civil works to commence - expected to take five to six months

Mid 2025: Commissioning and testing of IFB project

Training and Interpretive Centre

Oct 2024: Conceptual design for the Training and Interpretive Centre to be completed

Feb 2025: Detailed designs for the Training and Interpretive Centre by architect to start and completed in six to seven months with consultation

End 2025: Contractor appointed for construction of Centre

Stakeholder Engagement

To find out more about the FEITH project contact us on the link below:

Community and stakeholder engagement for Central Queensland

.